Before a coordinated OT or controls-network change, prove the exact aggregate scope and resulting topology, then demonstrate that rollback or stabilization remains executable when the changed path is degraded or unavailable.
Use before: Startup · Functional performance testing · Integrated systems testing · Installation turnover
Sources: Microsoft Azure · National Institute of Standards and Technology
Prove that source-transfer controls block every prohibited source combination and complete every required transfer before UPS autonomy becomes consequential.
Use before: Factory acceptance testing and submittals · Integrated systems testing · Functional performance testing · Installation turnover
Sources: Dranetz Technologies, Inc. · Microsoft Azure