What to check before the work begins
Before this live cutover proceeds, show the temporary power state at each consequential step, every affected load group whose redundancy changes, the adequacy of the remaining path and any finite bridge, and rollback executable from that step.
- Issue a controlled temporary one-line or step-state matrix
- Map each affected load group to its active, unavailable, and remaining paths
- Prove complete remaining-path adequacy and any finite-resource duration for work, credible delay, stabilization, and rollback
- Prove rollback without resources made unavailable by the work and resolve temporary-equipment, concurrent-work, and deficiency conditions
- Reconfirm field state, source availability, load, contingency basis, and responsible personnel immediately before release