What to check before the work begins
Before this source-transfer sequence is released, has the project proved every allowed and prohibited breaker/source state, every required transition, and the response to credible failed or contradictory status inputs within the available UPS bridge time?
- Approve a complete cause-and-effect and source-state transition matrix
- Verify every breaker and source status input point-to-point against the controlled logic version
- Prove positive close denial for every prohibited source combination
- Verify dead-bus, source-available, voltage, frequency, phase-sequence, synchronism, and other required permissives
- Challenge credible failed, stale, unavailable, or contradictory status inputs using a safe approved method
- Execute staged energized and representative loaded transfers through required states
- Measure end-to-end transfer time against the approved UPS bridge window and repeat after every correction