Hold technology-cooling-system connection or turnover until approved cleaning, flushing, cleanliness, chemistry, and applicable passivation evidence is accepted.
Use before: Installation turnover · Startup
Sources: ASHRAE, NEMA, and Pacific Northwest National Laboratory · Open Compute Project
Before cooling-system fill-and-flush wastewater is released, prove that the actual waste stream, discharge route, current receiving-authority acceptance basis, and an approved fallback disposition remain valid for that exact commissioning state.
Use before: Installation turnover · Startup
Sources: City of Cheyenne Board of Public Utilities · U.S. Environmental Protection Agency
After final quick-disconnect cycling and hose routing, prove each consequential liquid-cooling connection is fully engaged, mechanically supported within the project-approved envelope, and leak-tight in its final installed state.
Use before: Installation turnover · Startup · Functional performance testing
Sources: Colder Products Company (CPC) · Open Data Center Committee (ODCC) · Sohu / 数策Y字