What to check before the work begins
Hold TCS connection or turnover until project-approved cleaning, flushing, cleanliness, water chemistry, filtration, preservation, and where applicable passivation evidence is accepted.
- Hold TCS connection or turnover until project-approved cleaning, flushing, cleanliness, water chemistry, filtration, preservation, and where applicable passivation evidence is accepted.
- Approve material- and vendor-specific cleaning, flushing, filtration, chemistry, passivation, and preservation requirements.
- Protect TCS boundaries and capture representative cleanliness and chemistry evidence before connection.
- Accept results and exceptions against the project/OEM criteria before turnover.