Before integrated acceptance, prove every consequential fire or suppression input produces the required effects—and only the required effects—across power, HVAC, controls, and adjacent zones.
Use before: Startup · Functional performance testing · Integrated systems testing · Installation turnover
Sources: NASA Lessons Learned Information System / Jet Propulsion Laboratory · National Fire Protection Association · National Institute of Standards and Technology
Before discharge-capable acceptance or operational reliance, prove the as-built gaseous-suppression discharge is acoustically compatible with the actual magnetic HDD storage that remains exposed.
Use before: Installation turnover · Startup · Functional performance testing
Sources: Digi24, reproducing ING Romania statement · FM · Siemens · iTnews