What to check before the work begins
Before this representative loaded ATS transfer proceeds, has the project reconciled the actual normal and failover load, the capacity of every consequential path, and the complete installed trip settings against the current approved design, then demonstrated the transfer and retransfer under representative load?
- Reconcile current normal load and maximum credible coincident failover load for each affected ATS path
- Verify source, conductor, ATS, breaker, and downstream path ratings against that load
- Reconcile every installed ATS and upstream/downstream protective setting against the final approved protection and coordination basis
- Confirm the approved sequence of operations, transfer permissives, reset behavior, and restoration route
- Execute an approved representative loaded transfer and retransfer with synchronized event capture
- Disposition every unexpected trip, lockout, reset, overload, or manual intervention through the existing commissioning issue process